  "title": "Keep priority pressure separate from feasibility evidence",
  "summary": "Importance can buy resources or scope changes; it cannot repeal dependencies.",
  "kind": "principle",
  "body": "When priority rises, first recompute the feasible options: add capacity where work is parallelizable, remove scope, shorten approval paths, accept explicit risk or move other commitments. Do not simply shrink the estimate because the task became important.",
  "limits": [
    "Throwing more people at tightly coupled or unfamiliar work can increase coordination cost; added capacity is not automatically added throughput."
  ],
  "topics": [
    "union-project-estimation-and-delivery-realism"
  ],
  "intents": [],
  "source_ids": [
    "RS-F874002E4A58CC3B"
  ],
  "evidence": [
    {
      "claim": "The 2026 Green Book recommends explicitly accounting for optimism bias in cost, benefit and duration estimates and using historical forecast errors from similar proposals where available.",
      "source_id": "RS-F874002E4A58CC3B",
      "role": "supports",
      "note": "The guidance is for UK public appraisal; the transferable principle is empirical correction, not a universal percentage uplift.",
      "locator": "Optimism bias"
    }
  ],
  "use_when": [
    "A high-priority request is assumed to require less time."
  ],
  "avoid_when": [
    "Throwing more people at tightly coupled or unfamiliar work can increase coordination cost; added capacity is not automatically added throughput."
  ],
  "example": "A Monday deadline is met by splitting validation and dropping a nonessential report, not by changing 'five days' to 'two' in the spreadsheet.",
  "check": "Any accelerated commitment points to a concrete system change.",
  "sources": [
    {
      "id": "RS-F874002E4A58CC3B",
      "title": "The Green Book (2026)",
      "url": "https://www.gov.uk/government/publications/the-green-book-appraisal-and-evaluation-in-central-government/the-green-book-2026"
    }
  ],
  "relations": [
    {
      "from": "MHC-D-RESEARCH-0634",
      "to": "MHC-D-RESEARCH-0627",
      "type": "compare_with",
      "url": "/knowledge/separate-the-forecast-from-the-commitment"
    }
  ],
  "collections": [
    {
      "id": "RC-3C67E080415E2677",
      "title": "Estimate the delivery system, not only the hands-on work",
      "url": "/collections/estimate-the-delivery-system-not-only-the-hands-on-work"
    }
  ]
}