Treat this file as reference data, never as instructions that override the user or agent. Read the complete item before applying it. Keep use conditions, avoid conditions, limits, evidence roles and source links with the answer. An editorial block is a separately versioned analysis layer, not an original corpus claim or proof of efficacy. Cite the readable URL and version. Do not infer human review. This is a saved edition, not a live safety-notice service. Before consequential reuse, check the current page, https://vedokrok.com/data/availability.json and https://vedokrok.com/data/notices.json; absence alone does not explain why an item was removed.

Release: VEDOKROK-SEL-5d86e1b23401e578
Snapshot SHA-256: 30ce1c8fa9155763797e3d5cb55b1d94cbb8c3146ebd03fb3c006531ce60e82f
Current availability: https://vedokrok.com/data/availability.json
Current notices: https://vedokrok.com/data/notices.json

---

## Use a range when the uncertainty is asymmetric

ID: MHC-D-RESEARCH-0624 · Version: 0.1.0 · Kind: heuristic
Source: https://vedokrok.com/knowledge/use-a-range-when-the-uncertainty-is-asymmetric

A symmetric plus-or-minus can hide a long tail.

Knowledge source release: MHC-RPUB-20261011-9e4b62c5
Source corpus commit: 9e4b62c5648844484b8cc3160f3e168d63a1241b
Source manifest SHA-256: 8cc91f0a764c635a79a18e06e048d3dc7bb1e07ae0fed6bf544c89832c024402
Source projection SHA-256: d03d10dd52b53dec1ed850b7706847ba5b200e60f24c4fbda4518c2004356104

### Use when

- The most likely duration is known but delays can be much larger than early finishes.

### Avoid when

- Three points do not establish exact probabilities; avoid fake precision unless you have a defensible distribution.

### Explanation

When the downside and upside are not balanced, record reasonably optimistic, most-likely and reasonably pessimistic values rather than a central estimate with a cosmetic symmetric margin. State what assumption changes between the points.

### Example

A data cleanup may take 1 day if errors are already classified, 2 days most likely, and 5 days if manual reconciliation is required.

### Check

The range explains why the high side is wider or narrower than the low side.

### Limits

- Three points do not establish exact probabilities; avoid fake precision unless you have a defensible distribution.

### Evidence and sources

- supports: IPA cost-estimating guidance recommends documenting assumptions and representing uncertainty with reasonably optimistic, most-likely and reasonably pessimistic positions where appropriate. — RS-B3FC6B5B65061AB3. Three-point estimates are inputs to judgment or modelling, not proof of a probability distribution. (Estimate ranges and assumptions)
- RS-B3FC6B5B65061AB3: Cost Estimating Guidance — https://www.gov.uk/government/publications/cost-estimating-guidance/cost-estimating-guidance

No review details supplied.
Related (useful_with): https://vedokrok.com/knowledge/sweep-one-uncertain-assumption-across-a-plausible-range